TL;DR

A non-resident Indian booked a Rs. 2.30 crore apartment in the "Lodha Bellezza" project in Hyderabad in 2009, paying about 22% himself and the rest through a Rs. 2 crore HDFC housing loan disbursed directly to the builder under a tripartite agreement. The builder failed to deliver possession. The NCDRC ordered refund of the entire Rs. 2,19,92,107 to the buyer with 9% interest and held the bank deficient in service (Rs. 2,00,000). The Supreme Court held that refunding the whole amount to the buyer while the bank loan remained unpaid would be unjust enrichment. The buyer is entitled to refund only of the Rs. 1,27,34,726 he actually paid from his own pocket, with simple interest at 12% per annum as per Clause 24 of the Agreement for Sale, plus Rs. 15,00,000 compensation as full and final settlement of rent, mental agony and litigation expense claims. The finding of deficiency against the bank was upheld, and the balance deposit was kept aside pending the bank's recovery appeal before the High Court.

The Bottom Line

When a home loan has funded most of a flat that the builder never delivers, the buyer cannot take back the bank's money as if it were his own. The Supreme Court ruled that the refund belongs to the buyer only to the extent he actually paid from his own funds, with interest at the contractual 12%, and that the rest of the deposit must be preserved until the bank's separate claim against the buyer is decided by the High Court. The Court also refused rent claimed for more than a decade, holding that it would amount to double compensation, but awarded a lump sum of Rs. 15,00,000 for the long delay and agony. The bank's Rs. 2,00,000 liability for not verifying construction progress before releasing loan tranches stands.

Case Timeline

The journey from FIR to Supreme Court verdict

event
8 Aug 2009

Apartment Booked in Lodha Bellezza

The borrower, then a non-resident Indian, booked an apartment for Rs. 2,30,73,876 and paid a booking amount; he paid Rs. 51,11,576 (22%) from his own funds in total.

filing
21 Oct 2009

Agreement for Sale Executed

An Agreement for Sale was executed between the borrower and the Builder. Clause 24 fixed possession by 30 June 2011 with a six-month grace period and provided for 12% per annum interest/compensation on default.

filing
30 Jan 2010

Tripartite Agreement Signed

The borrower, the Builder and the Bank executed a Tripartite Agreement following the Bank's sanction of a Rs. 2 crore housing loan on 27 November 2009.

event
30 Jun 2011

Stipulated Possession Date Passes

Clause 24 required possession by 30 June 2011 (with a six-month grace period). Between February 2010 and July 2011 the Bank had disbursed Rs. 1,68,80,531 to the Builder in thirteen tranches, so that about 95% of the price had been paid. Possession was not delivered.

filing
13 May 2013

Consumer Complaint Filed

The borrower filed Consumer Complaint No. 150 of 2013 before the NCDRC seeking refund, interest, rent and compensation.

order
1 Jul 2022

NCDRC Orders Refund

The NCDRC directed the Builder to refund the entire amount with 9% interest and the Bank to pay Rs. 2,00,000 for deficiency in service. The Bank's review was dismissed on 7 December 2022.

order
10 Dec 2024

Commercial Court Dismisses Bank's Suit

The Commercial Court dismissed the Bank's recovery suit as not maintainable in view of the Commission's findings, without deciding the remaining issues. The Bank's appeal is pending before the High Court.

judgment
15 Oct 2026

Supreme Court Judgment

The Supreme Court modified the NCDRC order, limiting the refund to Rs. 1,27,34,726 with 12% simple interest, awarding Rs. 15,00,000 compensation and upholding the Bank's deficiency finding.

The Story

In 2009, M/s Lodha Healthy Constructions and Developers Private Limited (the Builder) launched a residential project called "Lodha Bellezza" at Kukatpally, Hyderabad. On 8 August 2009, the borrower, K. Madhusudhan Rao (now Madhu Kudapa), then a non-resident Indian, booked an apartment for Rs. 2,30,73,876. He paid Rs. 51,11,576, about 22% of the sale consideration, from his own funds, and an Agreement for Sale was executed on 21 October 2009.

For the balance, he approached Housing Development Finance Corporation Limited (the Bank). The Bank sanctioned a Rs. 2 crore housing loan on 27 November 2009. A Tripartite Agreement between the borrower, the Builder and the Bank followed on 30 January 2010, and a Loan Agreement dated 1 February 2010 was executed with the borrower and his wife as co-borrower. Between February 2010 and July 2011, the Bank disbursed Rs. 1,68,80,531 to the Builder in thirteen tranches, so the Builder had received about 95% of the sale consideration.

Under Clause 24 of the Agreement for Sale, possession was due by 30 June 2011, with a six-month grace period. The Builder missed it, later offered possession for "fit-outs" in late 2012 and informed the borrower on 25 March 2013 that the Fire Department NOC was awaited. Meanwhile the Bank debited pre-EMI interest; the borrower paid Rs. 26,23,150 towards it.

On 13 May 2013, the borrower filed Consumer Complaint No. 150 of 2013 before the NCDRC seeking refund of Rs. 2,19,92,107 with interest, house rent of Rs. 7,97,895 and compensation of Rs. 15,00,000. The Bank recalled the loan on 19 January 2015 and sued for Rs. 2,51,15,774 (COS No. 96 of 2017) before the Commercial Court. During the proceedings the borrower paid the Bank a further Rs. 20,00,000 and Rs. 30,00,000 in June and July 2021, bringing his total payments to the Bank to Rs. 76,23,150.

By order dated 1 July 2022, the NCDRC held the borrower a consumer, rejected the Builder's force majeure plea, ordered refund of the entire amount with 9% interest (12% on default), and directed the Bank to pay Rs. 2,00,000 for deficiency in service. The Bank's review was dismissed on 7 December 2022. The Builder did not appeal and deposited Rs. 4,43,24,510 with the Commission, which with interest stood at Rs. 5,65,43,411 on 8 October 2026. On 10 December 2024 the Commercial Court dismissed the Bank's suit as not maintainable in view of the Commission's findings, and the Bank's appeal is pending before the High Court. The borrower appealed over denial of rent, compensation and the rate of interest; the Bank appealed against the refund order and the finding of deficiency.

Legal Issues

Click each question to reveal the Supreme Court's answer

1Question

Whether the borrower is entitled to refund of the entire amount, including the amount disbursed by the Bank, and if so at what rate of interest?

Tap to reveal answer
1SC Answer

No. Applying the principle against unjust enrichment, the borrower is entitled in his own right only to Rs. 1,27,34,726 that he paid out of his own pocket (Rs. 51,11,576 to the Builder and Rs. 76,23,150 to the Bank), with simple interest at 12% per annum from the date of each payment, as agreed in Clause 24 of the Agreement for Sale. His claim for 18% was rejected.

Clarifies that a tripartite loan arrangement does not convert unpaid borrowed money into the buyer's own money for refund purposes, and that the contractual interest rate ordinarily governs.

2Question

Whether the borrower is entitled to compensation, including reimbursement of rent?

Tap to reveal answer
2SC Answer

Rent was refused for five reasons, including that it would amount to double compensation alongside interest and that the borrower elected the refund remedy under Clause 24. However, in view of the prolonged uncertainty and loss of price escalation, the Court awarded a lump sum of Rs. 15,00,000 as full and final satisfaction of all claims against the Builder for rent, mental agony, harassment and litigation expenses.

Sets limits on rent claims in builder-delay cases while allowing a reasoned lump-sum compensation.

3Question

Whether the Bank was deficient in rendering service to the borrower?

Tap to reveal answer
3SC Answer

Yes. The Bank produced no inspection reports or evidence that it verified construction progress before each of the thirteen disbursements, as its sanction letter required. The finding of deficiency is one of fact and the Rs. 2,00,000 compensation was upheld.

Lenders that disburse in tranches under tripartite agreements may be held deficient if they do not verify construction progress.

4Question

What relief is the Bank entitled to in these proceedings?

Tap to reveal answer
4SC Answer

The Bank's claim under the tripartite agreement cannot be adjudicated in a consumer complaint. The balance of the deposit is to remain in an interest-bearing account to abide by the outcome of the Bank's appeal before the High Court, which must decide it on its own merits, with all contentions left open.

Separates the buyer's consumer claim against the builder from the lender's recovery claim against the buyer.

Arguments

The battle of arguments before the Supreme Court

Petitioner

Vihaan Kumar

1

Borrower: full refund, 18% interest, rent and compensation

Senior counsel for the borrower argued that the loan was to be disbursed in step with construction but about 80% was released when the Builder lacked construction permission, that the Bank and Builder acted in collusion, that he should receive the entire amount (and repay the Bank if it succeeds), 18% interest, rent from 30 June 2011 to 1 July 2022 (at Rs. 38,000 per month and later Rs. 65,000 per month) and Rs. 35,00,000 of litigation expenses. He also argued that the Bank's appeal was barred by res judicata.

Rajnesh Sharma v. Business Park Town Planners Ltd., 2025 SCC OnLine SC 2061
2

Bank: no deficiency and refund violates the Tripartite Agreement

The Bank argued that refund of the entire Rs. 2.19 crore to the borrower violated Clauses 16 and 17 of the Tripartite Agreement, that by cancellation of the allotment it had been reduced from a secured to an unsecured creditor, and that the finding of deficiency was unsupported. It said res judicata did not apply because the suit was dismissed only on maintainability and its appeal was pending, and that its recovery rights could not be adjudicated in a consumer complaint.

Respondent

State of Haryana

1

Builder: accepted the NCDRC order and proposed a split

The Builder did not challenge the Commission's order. It submitted that out of the deposit, Rs. 1.27 crore paid by the borrower from his own pocket be refunded to him with such interest as the Court deemed fit, and the remainder with accrued interest be paid to the Bank. Alternatively it supported the order, saying 9% interest was adequate and that the borrower had himself quantified rent loss in a letter dated 3 November 2012.

Experion Developers (P) Ltd. v. Sushma Ashok Shiroor, (2022) 15 SCC 286DLF Homes Panchkula (P) Ltd. v. D.S. Dhanda, (2020) 16 SCC 318

Court's Analysis

How the Court reasoned its decision

The Court examined refund through the doctrine of unjust enrichment (nemo debet locupletari ex aliena jactura), noting its statutory footing in Sections 64, 65, 70 and 72 of the Indian Contract Act, 1872. It characterised the transaction as triangular: the Builder must refund what it received, but the money came from two sources. The deemed-disbursement fiction in the Tripartite Agreement fastens repayment liability on the borrower but does not make unpaid borrowed money his own. On interest, the parties' own Clause 24 fixed 12% and Rajnesh Sharma does not make 18% a rule of thumb. On compensation, the Court rejected rent as double compensation, outside the pleadings and proof, inconsistent with the borrower's election to take a refund and with his own earlier case, but awarded Rs. 15,00,000 as a lump sum. It upheld the finding of deficiency against the Bank and left the Bank's recovery claim to the High Court.

Restitution restores. It does not redistribute.

Para 25

Summarises the Court's approach to unjust enrichment as a doctrine of correction and not reward.

The law of contract compensates, it does not enrich.

Para 26

Frames the limit on compensation in buyer-builder disputes, cautioning against windfall gains.

It does not convert borrowed money, which remains unpaid, into the Borrower's own money.

Para 28

Explains why the deemed-disbursement clause in the tripartite agreement does not entitle the buyer to the bank's share of the refund.

cannot award interest and/or compensation by applying rule of thumb

Para 37

Quoting D.S. Dhanda, the Court reiterates that consumer fora must tie interest and compensation to the loss caused.

Partly Allowed

The Verdict

Relief Granted

Limited refund to the amount actually paid by the buyer, with 12% interest and Rs. 15,00,000 compensation; the rest preserved for the Bank's claim.

Directions Issued

  • The Commission shall release to the borrower Rs. 1,27,34,726 with interest at 12% per annum from the dates of the respective deposits made by him to the Builder and the Bank till payment.
  • The Commission shall release a further Rs. 15,00,000 to the borrower as compensation out of the deposit within one month, in full and final satisfaction of claims against the Builder for rent, mental agony, harassment and litigation expenses.
  • The remaining amount shall be kept by the Commission in an interest-bearing account to abide by the decision of the Bank's appeal.
  • The High Court shall decide the Bank's pending appeal on its own merits without being influenced by the observations in this judgment; all contentions on the borrower's liability under the loan are left open.
  • The Rs. 2,00,000 compensation payable by the Bank to the borrower for deficiency in service is upheld.
  • I.A. No. 95385 of 2026 is allowed only to permit the change of the appellant's name from K. Madhusudhan Rao to Madhu Kudapa; the borrower's proposed change of the respondents' description was not permitted.
  • No order as to costs.

Key Legal Principles Established

1

No one ought to be enriched at the expense of another; restitution restores and does not redistribute.

2

A deemed-disbursement clause in a tripartite agreement does not make the bank's unpaid loan money the buyer's own money for refund purposes.

3

Where the agreement fixes interest on builder default, strong reasons are required to depart from it; 18% is not a rule of thumb.

4

Rent and interest on the same refund amount cannot both be awarded for the same default (no double compensation).

5

A buyer who elects refund under the agreement cannot also claim rent for the apartment he gave up.

6

A lender that disburses against construction progress without verifying it may be held deficient in service.

7

A bank's recovery claim cannot be adjudicated in a consumer complaint by the buyer.

Key Takeaways

What different people should know from this case

  • If you buy a flat with a home loan paid directly to the builder and the builder fails to deliver, a refund may be limited to what you actually paid out of your own pocket, with the lender's share going back to the lender.
  • Check the agreement for sale: the interest rate stated for delay (here 12% per annum) is what a court is likely to enforce.
  • Claiming rent for years on top of interest on your money is unlikely to succeed, and rent claims must be pleaded and proved in the consumer complaint itself.
  • Banks releasing loan instalments to a builder are expected to check construction progress; failing to do so can mean compensation to the buyer.
  • Even after a consumer case, the bank may still pursue you for the loan in a separate proceeding.

Watch & Learn

Video explanations in multiple languages

Frequently Asked Questions

The Court held that the home buyer is entitled to a refund only of Rs. 1,27,34,726 that he paid from his own funds, with 12% simple interest, plus Rs. 15,00,000 compensation. The rest of the deposit is kept aside pending the Bank's appeal before the High Court.
Most of that money was paid to the builder by the Bank out of a loan that the buyer has not repaid. Giving it to the buyer while the loan was outstanding would amount to unjust enrichment, the Court held.
No. The Court held that rent along with interest would be double compensation, the claim went beyond the pleadings and proof, and the buyer had elected a refund under Clause 24 of the Agreement for Sale. A lump sum of Rs. 15,00,000 was awarded instead.
Yes. The finding that the Bank was deficient in service for not verifying construction progress before releasing the loan in thirteen tranches was upheld, along with the Rs. 2,00,000 compensation payable by it.
It cannot be decided in a consumer complaint. The Bank's appeal against the dismissal of its suit is pending before the High Court, which will decide it on merits, with all contentions of the Bank and the borrower left open.